Boteti Solar PV Facility (75 MW)

EIA-2026-003 · 🇧🇼 Botswana · Sese Energy (Pty) Ltd · Boteti District, near Letlhakane

EIA360° — Kalahari Environmental Consulting
Generated 6 Aug 2026

75 MW utility-scale solar PV plant with 132 kV grid-connection line to the Letlhakane substation; ~180 ha footprint on tribal land.

Stage
Authority review
Route
Full Environmental Impact Assessment
Competent authority
DEA
Environmental Authorisation
pending
1 · Screening determination
Solar generation > 5 MW and ≥132 kV line outside built-up areas — Schedule 1 (2021) EIA column → full EIA (s6(8)).
Screened 12 Jan 2026 by K. Mothibi (Reg. EAP, Snr)
2 · Statutory process record — Full Environmental Impact Assessment
StepActorStatutory clockCitationStartedCompleted / dueStatus
Project brief (Form A) submittedproponentEA Act s6(1)(a); reg 4, Form A12 Jan 202612 Jan 2026done
CA reviews project brief (3 working days)authority3 wdEA Act s6(3), s6(8)12 Jan 202615 Jan 2026done
Scoping publicity (≥ 10 working days) + community meetingspublic10 wdEA Act s7(2); reg 6, Form C16 Jan 20266 Feb 2026done
Scoping report (Form C) + ToR (Form D) submittedproponentEA Act s8; reg 6–76 Feb 20266 Mar 2026done
CA approval of ToR (10 working days)authority10 wdEA Act s8A(3)6 Mar 202618 Mar 2026done
EIS (Form E) prepared & submittedproponentEA Act s9(3); reg 8, Form E18 Mar 202625 Jun 2026done
Gazette + newspaper notice inviting comments (2 consecutive weeks)public14 dEA Act s10(2)(a)25 Jun 2026due 9 Jul 2026overdue
CA review of EIS (14 working days)authority14 wdEA Act s10(3)pending
Appeal window to Appeals Committee (30 days)public30 dEA Act s13(1)pending
3 · Public participation summary
3
registered I&APs
3
comments received
67%
responded / incorporated
Avifauna collision riskBirdLife Botswana (14 Apr 2026)Diverters specified every 5 m on earth wire in EIS s7.4; pre-construction survey added to the EMP.
Grazing accessKgosi L. Moroka (2 Apr 2026)Access corridor retained; fencing plan amended (EIS s6.2).
Local employmentBoteti District Council (28 Jun 2026)— awaiting response —
5 · Document register
Project Brief — Boteti Solar PVv1.0 · accepted · 12 Jan 2026
Scoping Report & ToRv2.0 · accepted · 6 Mar 2026
Environmental Impact Statementv1.0 · submitted · 25 Jun 2026