Authorisation conditions & audits

Authorisation conditions & audits

Environmental Clearance Certificate (ECC) · Commissioner compliance inspections (s17(2)(i)); environmental officers' entry/inspection powers (s19); compliance orders (s20 — non-compliance: fine ≤ N$500,000 or ≤ 25 years imprisonment).

Authorisation
ECC-2025-0847
granted with conditions · 20 Nov 2025
19 Nov 2028
valid until
1/4
conditions complied
0
breached

Conditions register

RefConditionDueStatusEvidence
ECC condition 3.1Management plan commitments form part of this certificate; annual compliance report to the Environmental Commissioner by 30 November each year.30 Nov 2026 · 116din progress
ECC condition 4.2Biodiversity offset area (68 ha) to be fenced and a management plan approved within 9 months of certificate issue.20 Aug 2026 · 14din progress
ECC condition 5.3PM10 monitoring results to be shared with the Southern Zinc Community Forum quarterly.15 Jul 2026 · 22d overopen
ECC condition 2.4No abstraction from the Orange River beyond the licensed allocation; abstraction records available on inspection.ongoingcomplied

Audit & inspection programme

DateTypeAuditorScopeFindingsMajorStatus
10 Jun 2026internalSRG IHH audit teamECC conditions + management plan commitments (construction phase)
Major: return-water dam freeboard breach (links CA-114). Minors: signage, spill-kit stock, training records.
41closed
15 Sept 2026authority inspectionOffice of the Environmental Commissioners17(2)(i) compliance inspection00planned